references Operations

Assessment of a Virtual Power Plant Slice

Project Run-Time

2009

Client

German energy supply company (regional supplier)

Objective

To decide on the conclusion of a long-term power supply contract (virtual slice of a power plant)

Our Tasks

  • To carry out a market survey on the long-term development of the German electricity generation market, including the development of electricity prices (fundamental analysis)
  • To assess the supplier contract by means of the survey´s results (as an individual project as well as taking into account the procurement situation of the energy supply company as a whole)
  • To recommend further actions (report)
  • To give support with contract negotiations

Result

Conclusion of a long-term supplier contract